Question: The Electric Distribution Network Construction project has the activity network diagram and estimated durations as shown below: Project: Electric Distribution Network Construction Duration (weeks Most

The "Electric Distribution Network Construction" project has the activity network diagram and estimated durations as shown below: Project: Electric Distribution Network Construction Duration (weeks Most Activity Optimistic Likel Pessimistic 12 35 30 18 A 30 Useful Formulas: most optimistic most likely 1 +41 +1 (1, -12) most pessimistic 6 6 expected duration vanance Using the PERT method, calculate the probability the project will be completed within 38 weeks: O 26% (Approx.) 16% (Approx.) 35% (Approx.) Q 45% (Approx.)