Question: - The % exceedance, flow and Tail Water Elevation ( TWE ) are given in the table below for a potential hydropower site. If the

-The % exceedance, flow and Tail Water Elevation (TWE) are given in the table
below for a potential hydropower site. If the headwater elevation is constant at 985
feet and the overall efficiency of the plant is 72%, what is the plant capacity factor
for a 21MW power plant?
a)0.96
b)0.89 The correct answer is ( b)0.89
c)0.64
d)1.0
- The % exceedance, flow and Tail Water Elevation