Question: ~ The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is?
~
The expected completion time for the project above is?
- 27 days
- 68 days
- 47 days
- 30 days
The critical path for the project is?
- B, C, F, H
- B, C, F, G, H
- A, C, F, G
- A, C, E, H
How much slack is there in activity G?
- 7 days
- 8 days
- 11 days
- 0 days (no slack)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts