Question: ~ The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is?

~

The expected completion time for the project above is?

  1. 27 days
  2. 68 days
  3. 47 days
  4. 30 days

The critical path for the project is?

  1. B, C, F, H
  2. B, C, F, G, H
  3. A, C, F, G
  4. A, C, E, H

How much slack is there in activity G?

  1. 7 days
  2. 8 days
  3. 11 days
  4. 0 days (no slack)

  1. ~ The expected completion time for the project
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A 4 12 A, B 15 A. B A. B C, D. E C, D. E H F. G 6 34) The expected completion time for the project above is