the expected demand in october is 20,000 units, and there are 25working days in october. the production
Fantastic news! We've Found the answer you've been seeking!
Question:
the expected demand in october is 20,000 units, and there are 25working days in october. the production rate is 10 units per dayper employee. The initial inventory is 1,000 units, and the endinginventory target is 5,000 units. following a chase strategy, howmany employees woul be needed in October?