Question: The expected (estimated) time for activity C is =? weeks. (Round your response to two decimal places.) The expected (estimated) time for activity for A

The expected (estimated) time for activity C is =?
weeks. (Round your response to two decimal places.)
The expected (estimated) time for activity for
A
B
C
D
E
F
G
H
I
J
K
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places.)