Question: The expected future cash inflows for the project are shown in the following table The firms current cost of capital is 10 Year Net Cash
The expected future cash inflows for the project are shown in the following table The firms current cost of capital is 10 Year Net Cash Inflows 0 5000000 1 2000000 2 3000000 3 1000000 4 2000000 Create a spreadsheet to answer the following questions 1 Calculate the projects net present value NPV 2 Calculate the projects internal rate of return IRR 3 Calculate the payback period for the project 4 Should the company accept the project based on the NPV IRR and Payback Period