Question: The expected ( most likely ) times for the project activities are given below. ID Description Predecessor Duration ( Day ) 1 Pilot production None
The expected most likely times for the project activities are given below.
ID
Description
Predecessor
Duration
Day
Pilot production
None
Select channels of distribution
None
Develop marketing program
Test market
Patent
Full production
Ad promotion
Quality check & Release
Find the expected project completion time
days
days
days
days