Question: The expected time for activity E is 100 days. How do you calculate that answer? Show me the formula with the numbers for this specific

The expected time for activity E is 100 days. How do you calculate that answer? Show me the formula with the numbers for this specific question. TYPED OUT. IE A(50) + B(90) = E (100).

Time Estimates (days) Activity

Precedes Optimistic Most Likely Pessimistic

Start A, B, C

A D 38 50 62

B E 90 100 108

C End 85 100 115

D F 19 25 31

E End 91 98 115

F End 62 65 68

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock