Question: The expected time for activity E is 100 days. How do you calculate that answer? Show me the formula with the numbers for this specific
The expected time for activity E is 100 days. How do you calculate that answer? Show me the formula with the numbers for this specific question. TYPED OUT. IE A(50) + B(90) = E (100).
Time Estimates (days) Activity
Precedes Optimistic Most Likely Pessimistic
Start A, B, C
A D 38 50 62
B E 90 100 108
C End 85 100 115
D F 19 25 31
E End 91 98 115
F End 62 65 68