Question: The Expected Value of a project's risk can be defined as: Select one: The sum of the probabilities of project risk events times the sum
The Expected Value of a project's risk can be defined as: Select one: The sum of the probabilities of project risk events times the sum of consequences of those risks The sum of the products of the probabilities of each project risk event times its consequence The sum of the consequences of all project risk events The sum of the probabilities of all project risk events None of the above