Question: The extruder setup for this problem is 3 cutters working at a rate of 2 1 cookies per minute per cutter. It takes 3 0

The extruder setup for this problem is 3 cutters working at a rate of 21 cookies per minute per cutter. It takes 30 seconds to load each batch of dough and an additional 38 seconds to clean each one of the cutters.
Given a batch size of 10 pounds of dough, the standard cookie size of 2 ounces, a shift length of 5 hours, find the capacity of the process in cookies per day. This will be a whole number.