Question: The figure below shows a project WBS with cost apportioned by percentages. If the total project cost is estimated to be $ 650,000, what is

The figure below shows a project WBS with cost
The figure below shows a project WBS with cost apportioned by percentages. If the total project cost is estimated to be $ 650,000, what is the estimated cost for "Requirements ? Router systems project Costs 650.000 Definition Design 10% Implementation 50N 40% Objectives 4% Requirements In house testing 401 Customer testing & review 6% 10% Inputs Files Outputs 3% Interfaces 35 33 Programming 22% 9 $ 58,500 $ 26,000 None of the other values provided $ 65,000 O$ 19,500 $39.000 Next Page Page 2 of 10