Question: The first process in developing a project schedule is to define all of the work activities. Now is the time to ask: What work activities

The first process in developing a project schedule is to define all of the work activities. Now is the time to ask: "What work activities must be completed to create each of these lowest level ______________?" a. milestones b. user stories c. requirements d. deliverables