Question: The first response to control this schedule is < > The second response to control this schedule is < > Earned Value Terminology Actual Cost
The first response to control this schedule is <
The second response to control this schedule is <
Earned Value Terminology
Actual Cost = (sum) actual cost of all work actually performed
Planned Complete = Work that should (as "Planned") be completed
Planned Value = (sum) approved budget for all work that should be completed [Budget x Planned Complete]
Actual Complete = Actual work completed
Earned Value = (sum) approved budget for all work that's actually completed [Budget x Actual Complete]
Original time estimate = the length of your critical path (time to complete the project in days)
Earned Value Calculations
| Actual Cost (AC) | $23,400 | Cost Variance (CV = [EV-AC]) | -100 |
| Planned Value (PV) | $32,600 | Schedule Variance (SV = [EV-PV]) | -9,300 |
| Earned Value (EV) | $23,300 | Schedule Performance Index (SPI = [EV/PV]) | 0.715 |
| Budget at Completion (BAC) | $200,100 | Cost Performance Index (CPI = [EV/AC]) | .996 |
| Scheduled Time to Complete (Original time estimate/SPI) | 28 days | ||
| Estimate to Complete (ETC = (BAC - EV) / CPI | $177,510 | ||
| Estimate at Completion (EAC = [ETC+AC]) | $200,910 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
