Question: The first step in the construction planning and scheduling process is identifying project activities. True False Question 5 4 1 pts The project plan establishes

The first step in the construction planning and scheduling process is identifying project activities.
True
False
Question 54
1 pts
The project plan establishes the order in which activities are to be completed and the planned sequence of construction.
True
False
Question 55
1 pts
The WBS is prepared
a and b
Concurrently with the CPM network
 The first step in the construction planning and scheduling process is