Question: The flexible - budget variance for materials is $ 2 , 0 0 0 ( U ) . The price variance for material is $

The flexible-budget variance for materials is $2,000(U). The price variance for material is $38,000(F). The efficiency variance for direct manufacturing labor is $12,000(F). Calculate the efficiency variance for materials.a. $18,000 unfavorableOb. $40,000 favorableOc. $6,000 favorableOd. $40,000 unfavorable