Question: The float (slack) of any activity in a PERT graph must be: Seleccione una: a. Zero or greater b. Zero c. Negative d. Positive Activity

The float (slack) of any activity in a PERT graph must be:

Seleccione una:

a. Zero or greater

b. Zero

c. Negative

d. Positive

Activity

Predecessors

Durations (days)

A

none

2

B

A

3

C

A

4

D

B

1

E

B and C

3

F

D and E

6

G

C and D

3

For the preceding project, the project duration is:

Seleccione una:

a. 15

b. 16

c. 18

d. 22

Activity

Predecessors

Durations (days)

A

none

2

B

A

3

C

A

4

D

B

1

E

B and C

3

F

D and E

6

G

C and D

3

For the preceding project, the earliest finish for activity F is:

Seleccione una:

a. 12

b. 16

c. 15

d. 9

An activity in a network has the following characteristics: ES = 10, EF = 18 and LS = 12. The duration of the activity is:

Seleccione una:

a. 6

b. 10

c. Cannot be determined with the information provided

d. 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!