Question: The float (slack) of any activity in a PERT graph must be: Seleccione una: a. Zero or greater b. Zero c. Negative d. Positive Activity
The float (slack) of any activity in a PERT graph must be:
Seleccione una:
a. Zero or greater
b. Zero
c. Negative
d. Positive
| Activity | Predecessors | Durations (days) |
| A | none | 2 |
| B | A | 3 |
| C | A | 4 |
| D | B | 1 |
| E | B and C | 3 |
| F | D and E | 6 |
| G | C and D | 3 |
For the preceding project, the project duration is:
Seleccione una:
a. 15
b. 16
c. 18
d. 22
| Activity | Predecessors | Durations (days) |
| A | none | 2 |
| B | A | 3 |
| C | A | 4 |
| D | B | 1 |
| E | B and C | 3 |
| F | D and E | 6 |
| G | C and D | 3 |
For the preceding project, the earliest finish for activity F is:
Seleccione una:
a. 12
b. 16
c. 15
d. 9
An activity in a network has the following characteristics: ES = 10, EF = 18 and LS = 12. The duration of the activity is:
Seleccione una:
a. 6
b. 10
c. Cannot be determined with the information provided
d. 8