Question: 2. Calculate the CUMULATIVE COST in February in below time-phased budget. Activity January February March April 8,000 5,250 Survey Design Dirt Foundation Framing Plumb
2. Calculate the CUMULATIVE COST in February in below time-phased budget. Activity January February March April 8,000 5,250 Survey Design Dirt Foundation Framing Plumb Wire 4,500 6,700 12,550 37,250 7,800 5,500 (4 marks)
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
The cumulative cost of February Total cost of ... View full answer