Question: 2. Calculate the CUMULATIVE COST in February in below time-phased budget. Activity January February March April 8,000 5,250 Survey Design Dirt Foundation Framing Plumb

2. Calculate the CUMULATIVE COST in February in below time-phased budget. Activity 

2. Calculate the CUMULATIVE COST in February in below time-phased budget. Activity January February March April 8,000 5,250 Survey Design Dirt Foundation Framing Plumb Wire 4,500 6,700 12,550 37,250 7,800 5,500 (4 marks)