Question: The flow rate through a process is 0 . 5 flow units per minute. The number waiting for the process is 1 . The time

The flow rate through a process is 0.5 flow units per minute. The number waiting for the process is 1. The time to do the activity in the process is 1 minute.
This is a stable system.
The number in process in the activity is Enter one integer (which can be 0) and two decimals, so the answer looks like X.XX. Any of the Xs can be a 0.
 The flow rate through a process is 0.5 flow units per