Question: The following are activities for developing and producing a Software system. draw a project network (30) compute (early & late) (start & finish) times for
The following are activities for developing and producing a
Software system.
- draw a project network (30)
- compute (early & late) (start & finish) times for each activity (25)
- determine slack (10)
- identify project duration (10)
- identify the critical path (25)
| ID | Task Name | Duration | Finish-start Predecessors | Finish-start Lag | Additional Lag Relationships | Lag |
| A | collect requirements | 2 wks | - | |||
| B | analyze processes | 3 wks | A | |||
| C | design processes | 6 wks | B | Start-Start task F | 3 wks | |
| Finish-Finish task F | 1 wk | |||||
| D | design screens | 1 wk | B | |||
| E | design reports | 2 wks | B | |||
| F | program | 4 wks | D, E | |||
| G | test | 8 wks | F | |||
| H | install | 2 wks | G |