Question: The following are data from a completed leveling job on a road. Prepare a set of profile leveling notes for the data using Collimation (

The following are data from a completed leveling job on a road. Prepare a set of profile
leveling notes for the data using Collimation (Height of Instrument) method and show the
page check. All data is given in feet. The elevation of BM A is 653.72, and the elevation of
BM B is 674.22.
Station BS IS FS Elev
BM A 5.98653.72
11+005.4
TP18.193.25
12+006.3
12+505.5
13+005.9
14+006.1
TP28.783.00
14+735.4
15+005.0
16+005.5
TP39.883.11
BM B 3.05674.2