Question: The following CPM/PERT network is for a small construction project with 8 activities labelled a through h , and activity times in weeks: The critical
The following CPM/PERT network is for a small construction project with 8 activities labelled a through h , and activity times in weeks: The critical path for this project is: a-d-f-ha-b-e-ha-b-ga-b-f