Question: The following data are given for 4 projects. Which one should be chosen? B D present value cost 205,000 130,000 105,000 250,000 350,000 present value

The following data are given for 4 projects. Which one should be chosen? B D present value cost 205,000 130,000 105,000 250,000 350,000 present value benefit 564,000 125,000 458,000 benefit/cost ratio 2.75 1.4 0.96 4.36