Question: the following data below, find: Normal Time (days) Cost Crash Time (days) Cost US es les Activitiy 1,2 1,3 2,4 2,5 3,4 4,5 80 150
the following data below, find:
Normal
Time (days) Cost
Crash
Time (days) Cost
US
es
les
Activitiy
1,2
1,3
2,4
2,5
3,4
4,5
80
150
60
100
140
60
490
80
- The network diagram
- Number of Paths (Durations for each path)
- Critical Path (Duration)
- Reduce the project to 10 days. Calculate the final cost. Now, what is the Critical Path
Given the following data below, find: 1. The network diagram 2. Number of Paths (Durations for each path) 3. Critical Path (Duration) 4. Reduce the project to 10 days. Calculate the final cost. Now, what is the Critical Path