The following data has been assembled for John Company. Use the high-low method.
Month | Cost | Hours |
January | $24,400 | 2,000 |
February | $39,000 | 2,200 |
March | $35,280 | 2,750 |
April | $36,400 | 3,500 |
May | $40,000 | 4,000 |
What is the expected total cost at an operating level of 1,900 hours?