Question: The following data is given for the Stringer Company: Budgeted production 26,000 units Actual production 27,500 units Materials: Standard price per ounce $6.50 Standard ounces

The following data is given for the Stringer Company:

Budgeted production 26,000 units
Actual production 27,500 units
Materials:
Standard price per ounce $6.50
Standard ounces per completed unit 8
Actual ounces purchased and used in production 228,000
Actual price paid for materials $1,504,800
Labor:
Standard hourly labor rate $22 per hour
Standard hours allowed per completed unit 6.6
Actual labor hours worked 183,000
Actual total labor costs $4,020,000
Overhead:
Actual and budgeted fixed overhead $1,029,600
Standard variable overhead rate $24.50 per standard labor hour
Actual variable overhead costs $4,520,000

Overhead is applied on standard labor hours. The direct materials quantity variance is

a.52,000 unfavorable

b.22,800 favorable

c.22,800 unfavorable

d.52,000 favorable

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!

Q:

\f