Question: The following data pertain to operations at Quick Incorporated: Throughput time .................... 4 hours Delivery cycle time ................ 8 hours Process time ......................... 1 hour

The following data pertain to operations at Quick Incorporated: Throughput time .................... 4 hours Delivery cycle time ................ 8 hours Process time ......................... 1 hour Queue time ........................... 2 hours 17. The wait time for this operation would be: A) 4 hours B) 2 hours C) 8 hours D) cannot be determined from information provided 18. The combined inspection and move time for this operation would be: A) 4 hours B) 1 hour C) 2 hours D) cannot be determined from information provided 19. The manufacturing cycle efficiency (MCE) for this operation would be: A) 50% B) 75% C) 25% D) 12'%