Question: The following data regarding the activity-based costing system at the Company Co. is available: Activity Pool Base Budgeted Activity Budgeted Cost Machine set up #
| The following data regarding the activity-based costing system at the Company Co. is available:
In addition, prior to adopting an activity based costing system, Company Co. applied overhead based on direct labour hours. The budgeted total labour hours for the year was 54645. If one job required 424 direct labour hours, 39 setups, 50 orders, and 24 hours of shipping time what is the difference between the overhead assigned using the traditional method and ABC?
Select one: a. $1264 b. $3438 c. $4408 d. $5672 | |||||||||||||||||||||||