The following data relate to the direct materials cost for the production of 1,800 automobile tires:
Actual: | 59,800 lb. at $1.90 |
Standard: | 61,600 lb. at $1.85 |
a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Price variance | $fill in the blank 1 | Unfavorable |
Quantity variance | $fill in the blank 3 | Favorable |
Total direct materials cost variance | $fill in the blank 5 | Favorable |