Question: The following data represent a network for a small project. (8 Points Total) All times are in weeks; and the network proceeds from node 1

The following data represent a network for a small project. (8 Points Total) All times are in weeks; and the network proceeds from node 1 to node 6.

Activity Initial Node Final Node Estimated Duration A 1 2 4 B 2 3 6 C 2 4 2 D 1 4 3 E 3 4 5 F 3 5 1 G 4 6 10 H 5 6 8

a. Draw a network diagram representing the project below. (3 points).

a. Determine how many paths there are in this network diagram, and write the paths and their lengths below (3 points).

a. Based on the information, what is the least duration of the project? (1 point)

a. Identify the critical path and list the activities which fall under it? (1 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!