Question: The following data represents the manufacturing lead - time for a composite air baffle at a factory. There is an order for 5 0 units

The following data represents the manufacturing
lead-time for a composite air baffle at a factory.
There is an order for 50 units with production
activities taking place in work centers A and B.
Calculate and provide answer as follows:
i) Total manufacturing lead time for the order.
(Convert answer to hours and minutes)
ii) Actual percentage of time the order is
running.