Question: The following dependency matrix represents a project with five activities (A, B, C, D, E). B C D E B D E mill001 The expected

The following dependency matrix represents a
The following dependency matrix represents a project with five activities (A, B, C, D, E). B C D E B D E mill001 The expected duration of each activity in days is as follows: 8 B D E 7 wu w Consider the choices below. Which pair of activities is it possible to complete in parallel because they do not depend on one another? OB and D A and D O A and C OB and E None of these Consider the choices below. Which activity or activities has no successor(s)? E only OAB, and E O A and B B only