The following exercise involves the information in the figure shown below on constructing a home.
Task Length Dependency
a. Write and agree on contracts 3 weeks
b. Secure financing 4 weeks a
c. Obtain permits 6 weeks a, b
d. Site work 4 weeks a, b, c
e. Build foundation 3 weeks b, c, d
f. Erect walls 3 weeks d, e
g. Build roof 5 weeks f
h. Rough in plumbing 2 weeks f
i. Rough in electrical 2 weeks f
j. Rough in furnace and air conditioning 1 week f
k. Finish exterior 6 weeks f, g, i
l. Finish interior 6 weeks f, g, h, i, j
m. Finish plumbing 2 weeks h, i
n. Finish electrical 1 week i, l
o. Finish furnace and air conditioning 1 day j, l
p. Wait for inspection 2 weeks k, l, m, n, o
If the project proceeds on schedule, how much time should have elapsed before the roof is built? If appropriate, give a range of time.
Roof building should begin after
weeks and should end after
weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!