Question: The following exercise involves the information in the figure shown below on painting a room. Task Length Dependencies a . Select paint color 3 days

The following exercise involves the information in the figure shown below on painting a room.
Task Length Dependencies
a. Select paint color 3 days
b. Calculate square footage of area to be painted 45 minutes
c. Buy paint 1 hour a, b
d. Buy drop cloths, brushes, rollers, TSP, tape 1 hour
e. Wash walls with TSP 4 hours d
f. Remove lights, plug covers and switch covers 30 minutes
g. Tape walls and windows alongside trim 1 hour d
h. Paint trim 3 hours c, d, e, g
i. Let trim paint dry 3 hours h
j. Remove wall tape 30 minutes i
k. Tape trim alongside walls 1 hour d, i
l. Paint walls 3 hours c, d, e, f, g, h, k
m. Let wall paint dry 3 hours l
n. Remove trim tape and window tape 30 minutes m
o. Replace lights, plug covers and switch covers 30 minutes m
p. Clean brushes, rollers 30 minutes l
q. Dispose of drop cloths, tape 15 minutes n
How many workers would it take to finish the painting job within the completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!