Question: The following five jobs will be processed through two work centers at a printing press. The sequence is the first printing, then binding. Processing time

The following five jobs will be processed through two work centers at a printing press. The sequence is the first printing, then binding. Processing time at each of the work centers is shown in the following table. Required: What is the optimal sequence for these jobs to be scheduled