Question: the following five multiple-choice questions based on Chapter 8 in the Microsoft Project Which field has Start, Finish, Duration, Work and Timephased work, and Cost

the following five multiple-choice questions based on Chapter 8 in the Microsoft Project Which field has Start, Finish, Duration, Work and Timephased work, and Cost and Timephased cost? Group of answer choices Resource Fields Assignment Fields Task Fields All of the above