Question: The following information has been compiled for a project that is about to begin. Assume the time estimates were made at the 9 9 +

The following information has been compiled for a project that is about to begin. Assume the time estimates were made at the 99+ percent level.
\table[[Activity,\table[[Preceding],[Activities]],\table[[Optimistic],[Time]],\table[[Most],[Likely]],\table[[Pessimistic],[Time]]],[A,None,6,7,14],[B,None,8,10,12],[C,A,2,3,4],[D,A,6,7,8],[E,B, C,5,5.5,9],[F,B, C,5,7,9],[G,D, E,4,6,8],[H,F,2.5,3,3.5]]
a) Construct the network (10 points).
b) What is the probability that the path with the longest expected duration will be completed 21 days? (10 points)
c) Assuming the paths are independent, what is the probability that the project will be comple within 21 days? (5 points)
 The following information has been compiled for a project that is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!