Question: The following information has been computed for a project: Expected total time is 180 days with a standard deviation of 12 days. Show your work.
The following information has been computed for a project: Expected total time is 180 days with a standard deviation of 12 days. Show your work. Round to 4 decimal places. Circle/highlight your answers. (6pts)
- What is the probability that the project will be completed 20 days before its expected completion date of 180 days? 3pts.
- If you would like to be 95% certain that the project will be finished before the due date, what due date (project duration in days) would you ask for? 3pts.