Question: The following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is

The following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusion