Question: The following information is given for a CPM network: Normal Normal Crash Crash Activity Predecessor Successor Time Cost Time Cost A - - - B

The following information is given for a CPM network:
Normal Normal Crash Crash
Activity Predecessor Successor Time Cost Time Cost
A --- B, C 5 $602 $125
B A D, C 470290
C A, B D 6803150
D B, C ---340160
What is the normal project completion time, given the information above?
11
13
14
16
None of the above.