Question: The following information relates to a project ( note: task times are in weeks ) . Use the information to solve for the critical path

The following information relates to a project (note: task times are in weeks). Use the information to solve for the critical path and then to determine the completion time that would provide a 90% chance of success.
Activity Immediate Predecessor to tm tp
A -5913
B A 61014
C A 101418
D B 4812
E C 111417
F D, E 3813
Part 2
Choose the correct activity-on-node (AON) diagram below.
Standard Normal Table
Probability (%)
z value
901.28
951.65
982.05
992.33
The completion time for the project is how many weeks? (Enter your response rounded to one decimal place.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!