Question: The following information relates to a project ( task times are in weeks ) . Use the information to solve for the critical path and
The following information relates to a projecttask times are in weeks Use the information to solve for the critical path and then to determine the probability that the project could be completed within weeks.
Task
Preceding Tasks
t Subscript o
t Subscript m
t Subscript p
A
None
B
A
C
A
D
B
E
C
F
D E
LOADING... Click the icon to view the table of standard normal probabilities.
Part
The probability that the project is completed within weeks is
enter your response here. Enter your response rounded to four decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock