Question: The following information was provided for a project Immediate Activity Predecessors A - B A C A D B, C E C F D, E

The following information was provided for a project

Immediate

Activity Predecessors

A -

B A

C A

D B, C

E C

F D, E

The number of hours needed to complete each activity as follows.

Activity Optimistic time Most Likely Time Pessimistic Time EXPECTED TIME VARIANCE
A 1 2 3
B 1 2 2
C 2 3 4
D 3 5 6
E 4 5 6
F 3 6 7

a. Using the data above, develop a network for this project. (5 marks)

b. Use PERT to identify the expected time and variance for each activity. (5 marks)

c. Determine the early and late times for each activity (5 marks)

d. Determine the critical path and expected completion time of the project (5 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!