Question: The following is known about a project Task Imm Pred Duration A - 9 B - 4 C B 7 D A 5 E C,D
The following is known about a project
Task Imm Pred Duration
A - 9
B - 4
C B 7
D A 5
E C,D 3
F D 11
G E 4
1- Draw a network diagram in excel
2- Compute early and late start and finish times
3- What is the expected project completion time?
4- What is the critical path?