Question: The following is known about a project Task Imm Pred Duration A - 9 B - 4 C B 7 D A 5 E C,D

The following is known about a project

Task Imm Pred Duration

A - 9

B - 4

C B 7

D A 5

E C,D 3

F D 11

G E 4

1- Draw a network diagram in excel

2- Compute early and late start and finish times

3- What is the expected project completion time?

4- What is the critical path?