Question: The following is the activity list for a project: Activity Predecessor Normal duration (weeks) Crash duration (weeks) Normal cost Crash cost A -- 3 2

The following is the activity list for a project: Activity Predecessor Normal duration (weeks) Crash duration (weeks) Normal cost Crash cost A -- 3 2 $12,000 $24,000 B A 5 4 $20,000 $22,000 C A 4 3 $1