Question: The following is the earned value chart for a project. Which is NOT correct about this earned value chart? At this moment, the completed less
The following is the earned value chart for a project.
Which is NOT correct about this earned value chart?
At this moment, the completed less work than what they were supposed to complete.
If they continue the current trend, they will need more resource than what was originally allocated.
At this moment, they spent more than what they were supposed to spend.
Planned value linearly increases by elapsed time.