The following jobs are waiting to be processed at Julie Morel's machine centre: Job Date Order Received
Fantastic news! We've Found the answer you've been seeking!
Question:
The following jobs are waiting to be processed at Julie Morel's machine centre:
Job
Date Order
Received
Production Days
Needed
Date Order
Due
A
B
C
D
E
The first day the task arrives is the first day that the job is being done.
In what sequence would the jobs be ranked according to the following rules: a FCFSb EDD, c SPT andd LPT All dates are according to shop calendar days. Today on the planning calendar is day and none of the jobs have been started or scheduled. Which rule is best?
Part
a Using the FCFSfirst come, first served decision rule for sequencing the jobs, the order is:
Sequence
Job
B
Part
A
Part
D
Part
E
Part
C
Part
The total flow time for the sequence developed using the FCFS rule is enter your response here days round your response to two decimal places