Question: The following partial information is contained in the variance analysis received from the Western Plant of Eastlawn Company. All plants at Eastlawn apply overhead
The following partial information is contained in the variance analysis received from the Western Plant of Eastlawn Company. All plants at Eastlawn apply overhead on the basis of direct labor-hours. Flexible budget for variable overhead based on 3,600 direct labor-hours Actual total overhead incurred Actual direct labor-hours worked Direct labor-hours used to determined the fixed overhead application rate Price variance for variable overhead Price variance for fixed overhead Required: a. Prepare a variable overhead analysis. b. Prepare a fixed overhead analysis. $ 100,800 $ 504,300 3,712 3,350 $ 6,950 F $12,014 U
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
a Variable Overhead Analysis Actual variable overhead incurred 100800 Actual direct laborhours worke... View full answer