Question: The following performance data is provided for an IT project at Best University. You are at the end of month 4. Use the data to

  1. The following performance data is provided for an IT project at Best University. You are at the end of month 4. Use the data to determine the various performance measures specified below the table. Assume that the cost of each activity is linearly distributed over its duration. You may use Excel for this question.

Activity

Duration (months)

Predecessors

Total Budgeted Cost ($)

% complete after 4 months

Actual Cost of all tasks after 4 months =$21,800

A

3

-

9,000

100

B

4

-

10,000

25

C

2

A

7500

100

D

4

A

12,000

25

E

2

C

2500

50

F

3

C

10,500

0

G

2

E, F

4,500

0

H

2

-

4000

0

Determine the following for the entire project

(i) cost variance

(ii) schedule variance

(iii) Cost performance index

(iv.) Schedule performance index

(v) Critical ratio

(vi) the estimated cost at completion (new budget)

(vii) the estimated time at completion (i.e., new duration)

Provide appropriate interpretations for each variance and ratio

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!