Question: The following portion of a WBS (work breakdown structure) project plan lists the project tasks (labelled by letter), the tasks on which they are dependent,

The following portion of a WBS (work breakdown structure) project plan lists the project tasks (labelled by letter), the tasks on which they are dependent, and their estimated duration (in days). You can assume Saturday and Sunday are not work days for the project.

The following portion of a WBS (work breakdown structure) project plan lists

(i) Using the information given, create a Pert chart, clearly indicating the dependencies on the Pert chart and mark the critical path on the chart. Show your workings.

\begin{tabular}{|c|c|c|} \hline Task Name & Dependency & EstimatedDuration(days) \\ \hline A & None & 3 \\ \hline B & None & 5 \\ \hline C & A & 3 \\ \hline D & A, B & 5 \\ \hline E & C & 4 \\ \hline F & C, D & 5 \\ \hline G & E & 3 \\ \hline H & G & 4 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!