Question: The following probabilistic activity time estimates are for the network in Problem 9.6: Time Estimates (Months) Activity a m b 1 4 8 12 2

The following probabilistic activity time estimates are for the network in Problem 9.6: Time Estimates (Months) Activity a m b 1 4 8 12 2 6 10 15 3 2 10 14 4 1 4 13 5 3 6 9 6 3 6 18 7 2 8 12 8 9 15 22 9 5 12 21 10 7 20 25 11 5 6 12 12 3 8 20 Determine the following:

The following probabilistic activity time

For the CPM/PERT network determine the probability that the network duration will exceed 50 months.

Activity m b 1 4 8 12 2 6 10 15 3 2 10 14 4 1 4 13 5 3 6 9 6 3 6 18 7 2 8 12 8 9 15 22 9 5 12 21 10 7 20 25 11 5 6 12 12 3 8 20 Activity m b 1 4 8 12 2 6 10 15 3 2 10 14 4 1 4 13 5 3 6 9 6 3 6 18 7 2 8 12 8 9 15 22 9 5 12 21 10 7 20 25 11 5 6 12 12 3 8 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!